Construction of the Cairns Road scheme started on 4 March 2019.

The scheme will install a parallel crossing at the junction of Cairns Road/Coldharbour Road. Once complete, this crossing will make it easier for people walking and cycling to cross the road.

The scheme will be built in five phases.

  • Phase 1 South Corner 04/03/19 – 20/03/19
  • Phase 2 Eastern Corner 21/03/19 – 28/03/19
  • Phase 3 North Corner 29/03/19 – 10/04/19
  • Phase 4 West Corner 11/04/19 – 01/05/19
  • Phase 5 Rear of 190 Coldharbour Road 02/05/19 – 08/05/19