Please click here for important travel advice regarding Coronavirus.

x
3

Major Updates

The MetroWest Phase 1 project is proposing to re-open the Portishead rail line to passenger train services and to enhance local passenger train services on the Severn Beach and Bath to Bristol lines.

Upgrading the train service for the Severn Beach Line, the Bath Spa to Bristol Line, and reopening the Portishead Line to passenger services is a priority for the West of England’s local authorities. It will increase the UK’s passenger rail network by 14 kilometres (9 miles), connect an additional 50,000 people to the rail network and improve the existing train service for 180,000 people within 1 kilometre of existing stations.

The plans include a new rail station at Portishead and the reopening of the former station at Pill. The project is subject to funding and meeting all the regulatory and technical requirements.

The project is led by North Somerset Council on behalf of the four West of England councils: Bristol City; Bath & North East Somerset; North Somerset and South Gloucestershire.

Documents about the MetroWest Phase 1 project – including the DCO application, plans, business case, consultation reports and environmental information – can be viewed on the document store website


Large Local Major Schemes: Bid for construction funding - December 2017

In December 2017, the West of England LEP and the promoting authorities (Bath & North East Somerset, Bristol City, North Somerset, South Gloucestershire and the West of England Combined Authority) submitted a funding bid for MetroWest Phase 1 to the Department for Transport’s Large Local Major Schemes programme. The bid consists of:

(a) Completed bid template (Part One)
(b) Checklist to highlight where key information can be found in the Outline Business Case (Part two)
(C) Outline Business case

The Outline Business Case details the scheme’s preferred option with an identified defined scope, detailed costs and appraisal and a firm delivery plan for construction. The Department for Transport will decide which bids receive funding for construction as part of a competitive process.

All documents submitted are now available to view using the links below.


Ashton Vale Road Level Crossing

We completed highway traffic modelling to determine the traffic impact of our proposed service for the Portishead line.

Our modelling shows that the existing Ashton Vale Road level crossing can remain open with specific mitigation and it won’t be necessary to provide alternative highway access to the Ashton Vale Industrial Estate.

Our proposals are to:

  • Extend the length of the left turn flare lane on Winterstoke Road for vehicles turning in to Ashton Vale Road;
  • Optimise the phasing of the Winterstoke Road  junction traffic signals by using a Microprocessor Optimised Vehicle Actuation (MOVA) system which responds to live traffic volumes by adjusting and optimising the timing of traffic signal phases to make best use of the available capacity; and
  • Install a ramp to the north of the level crossing to connect pedestrians and cyclists from Ashton Vale Road to Ashton Road and the existing network of at grade and subway footpaths and cyclepaths.

We have used the results of our highway traffic modelling to produce the following videos which show the traffic impact of our scheme in the AM and PM peak hours.


Consultation updates

Portishead Branch Line Consultation 2015

  • Consultation Report

    Below is the consultation report and appendices from the Development Consent Order Stage 1 consultation for MetroWest Phase 1. The consultation took place from 22 June to 3 August 2015.

    The report contains the results of the questionnaire and feedback from everybody who took part in the consultation.

    95% or respondents supported the proposals either entirely or mainly.

    Based on your feedback, we will refine our plans and hold another consultation in 2016 when we will hold further exhibitions. We will then make final amendments to our planning application and submit to the Secretary of State.

    Consultation report

  • Statement of Community Consultation

    This Statement of Community Consultation (SoCC) has been published in accordance with Section 47 of the Planning Act 2008, and explains how we will keep you informed throughout the development process as well as how you can comment on the proposals and help shape the project. It also provides information on the wider MetroWest Phase 1 proposals.

    Statement of Community Consultation

  • Environmental Information

    The Environmental Impact Assessment regulations require us to produce and consult on Preliminary Environmental Information (PEI). The PEI for this stage of the consultation comprises an environmental scoping report and a baseline report. Please note that these are large files, at over 25mb each. If you have difficulties downloading the files please let us know and we will provide them in a different format.

    Scoping Report

    Baseline Report

Further Updates

  • Further section 42 consultation from 30 August to 1 October 2019 closed

    In August 2019, following our review of title and Land Registry information, we further identified those with an interest in some of the land required for, or affected by, the proposals to re-open the Portishead branch line. We have contacted affected parties directly with details of how to respond. The consultation is now closed. Thanks to those who took part. For reference, the documentation listed in the correspondence can be viewed by clicking the link below:

    MetroWest Phase 1 document store

  • Development Consent Order for Phase 1 is to be submitted to the Government for formal approval

    At a Full Council meeting in June 2019, North Somerset Council agreed to submit a Development Consent Order (DCO) application to the Planning Inspectorate for the £116m MetroWest Phase 1 scheme. The DCO application seeks powers to build and operate the disused section of railway from Portishead to Pill, gain environmental consent to undertake works to the existing freight railway through the Avon Gorge and obtain powers for the compulsory acquisition of land. Councillors also agreed to enter into a new formal agreement with Network Rail.

    Relaunching train services from Portishead with new stations at Portishead and Pill is a key part of the first phase of the MetroWest programme of transport improvements across the region being led by the West of England Combined Authority (WECA) and North Somerset Council.

    The West of England Joint committee has also confirmed a £500,000 allocation to the MetroWest scheme, following the Transport Secretary’s commitment of an extra £31.9m to complete the funding needed. The Severn Beach line extension to Bath and Westbury is also on track for 2021.

    Once the application is registered by the Planning Inspectorate, the Secretary of State for Transport is expected to make a decision within 18 months.

    Subject to final business case approval, construction work is expected to start on the Portishead to Bristol line in December 2021 and take around two years to complete.

  • Funding secured for Portishead Rail

    In April 2019, MetroWest Phase 1 received over £31m funding from the Department for Transport (DfT). The announcement was made by Chris Grayling, the Secretary of State for Transport at a visit to Portishead. The funding announcement comes ahead of the submission of a Development Consent Order (DCO) to the Government this Summer. All nationally-significant infrastructure projects require a DCO before they can progress.

    As well as reopening the Portishead Rail branch line, with two new stations at Portishead and at Pill, this MetroWest scheme also includes vital improvements to passenger services along the Severn Beach and Bristol to Bath Lines.

  • Stage 2 consultation report

    The Stage 2 Consultation on re-opening the Portishead branch line as part of MetroWest Phase 1 was held from 23 October to 4 December 2017.

    We received over 1,000 responses from members of the community, statutory bodies, landowners and other interested parties. Issues raised have been captured and considered in the Stage 2 Consultation Report which is now available and will help develop the scheme.

    We will continue to engage with individual stakeholders on outstanding issues or concerns regarding the development of the project as we finalise the application for a Development Consent Order (DCO). Thank you to everyone who took part.

    Read the consultation report

  • Further section 42 consultation from 15th February to 19th March 2019 now closed

    In February 2019, following our review of title and Land Registry information, we further identified those with an interest in some of the land required for, or affected by, the proposals to re-open the Portishead branch line. We contacted affected parties directly with details of how to respond. The consultation has now closed, thank you to those who took part. The documentation that was listed in the correspondence can be viewed by clicking the link below.

    MetroWest Phase 1 document store

  • Large Local Major Schemes: Bid for construction funding - December 2017

    In December 2017, the West of England LEP and the promoting authorities (Bath & North East Somerset, Bristol City, North Somerset, South Gloucestershire and the West of England Combined Authority) submitted a funding bid for MetroWest Phase 1 to the Department for Transport's Large Local Major Schemes programme.

    More information, and a link to all documents submitted, can be found on this page.

  • Stage 2 Consultation on re-opening the Portishead branch line as part of MetroWest Phase 1

    Our Stage 2 Consultation was held from 23 October to 4 December 2017. The consultation has now closed.

    Thank you to everyone who took part. We will consider all the responses we received and will publish a report in early 2018.

    Detailed information about MetroWest Phase 1, including the information presented in our Stage 2 consultation, is available to view at our document store website.

    MetroWest Phase 1 document store

Subscribe to travel updates, news, and offers

By signing up you are agreeing to our terms and conditions and privacy policy Preferences